01 · The challenge
A go-live date at risk, with no time to restart
Delivery had slowed, stakeholder confidence had dropped and the January 2024 go-live was under threat. Restarting would have cost the date, and medical device compliance, consignment inventory and multi-country operations left no room for more delay. The company needed a partner to stabilize the program in flight.
02 · The approach
Stabilize first, then deliver
TSP entered in an advisory and recovery role, then took over full delivery.
The four phases
Recovery
Assessed the program, validated decisions already made, and restored planning for testing, cutover and readiness.
Go-live
Led technical and functional delivery across FICO, SD, MM, EWM, PP, integration, Fiori, ABAP and security.
Global template
Designed a template that standardizes operations and allows for local regulations, then delivered the first international rollout.
Support
SLA-based application management with 24x5 coverage and audit-ready processes.
03 · The results
Live on the date that mattered
- US go-live on January 1, 2024, the original committed date
- A global template in place, with the first international rollout live and more planned
- Long-term application management and optimization across logistics, finance and manufacturing